F03 – Have Program Closure peer-reviewed
This management activity belongs to the Program Closure group. The activities in this group tie up the loose ends and close the program when it’s complete or canceled.
This is a draft of the manual for review. If you have any comments, please email them to info@omimo.org. Please check back for the final version.
What
Ask another program manager or program management expert in your organization to review your management activities to make sure everything is OK.
Why
This peer review is done for two main reasons:
- To make sure you’re ready to end this activity group and the program as a whole, and that there are no serious mistakes.
- To generate useful information you can use to improve your organization-wide program management system as well as allowing the two program managers to learn from each other.
Who
It’s the responsibility of the program manager to find the peer reviewer, make the arrangements, and conduct the session.
How
The program manager and the peer spend some time together going through program documents and making sure everything is fine; e.g., the target Scenario is updated with the latest facts and there are no open items in the Follow-Up Register.
Store the overall result in the Health Register. If there are any adjustments you want to make, create items for them in the Follow-Up Register.