B01 – Revise all Scenarios and refine the target Scenario

This management activity belongs to the Monthly Initiation group. The activities in this group revise the plans and decide whether it’s a good idea to continue the program.


This is a draft of the manual for review. If you have any comments, please email them to info@omimo.org. Please check back for the final version.

What

Based on what you’ve learned from the environment, revise all Scenarios to make them more realistic and ready to be followed if needed. Then, spend extra time on the target Scenario and make it more refined for the next few cycles.

Why

First, any type of plan must be continually updated to remain useful, and your viable Scenarios are no exception to that. Because of the high level of uncertainty in programs, it’s not realistic to detail everything upfront, but you should start with a high-level Scenario and keep adding more details to the target Scenario once a month.

Besides the target Scenario, you must keep other Scenarios up to date as well. That’s necessary because you may have to switch Scenarios, not only because the target Scenario is not as good as you thought it would be, but also because one of the other viable Scenarios has become much better than you thought it would be — so much so that you prefer to put your target Scenario aside and switch to it. Such an opportunity exists only when you keep all your Scenarios up to date in this activity.

Who

The solution ideation team revises and refines the Scenarios under supervision from the program manager.

How

The solution ideation team goes through each Scenario and adjusts it based on the new realities they are in. This includes

The idea is that each Scenario should be ready to take over the program from the target Scenario. The performance information from the projects that are ongoing under the program is an important source of updates for the Scenarios.

For the target Scenario, you should add details for the next cycle or the next few cycles. It should not be too detailed, though, because it’s up to the projects to make their part more detailed. The appropriate level of detail at the program level is one that helps the teams initiate projects and judge the viability and justification of the target Scenario.

For projects that you’re supposed to initiate during the month, a Business Case should be prepared beforehand in this activity. You should also appoint the sponsor of the project in this activity.